Senior management appoints you as the project manager to be responsible for the company's newly launched ERP deployment project. In the startup phase, senior management wants you to be able to estimate the duration quickly, but not too accurately. Which estimation technique should you use:
A, analogical estimation
B, bottom-up estimation
C, three-point estimation
D, unable to estimate
12.6 answer: a, organizational system is not a technology for product decomposition. Product analysis technology includes: product decomposition, demand analysis, system analysis, system engineering, value analysis, value engineering and so on.