Senior management appoints you as the project manager to be responsible for the company's newly launched ERP deployment project. In the startup phase, senior management wants you to be able to estimate the duration quickly, but not too accurately. Which estimation technique should you use:

A, analogical estimation

B, bottom-up estimation

C, three-point estimation

D, unable to estimate

12.6 answer: a, organizational system is not a technology for product decomposition. Product analysis technology includes: product decomposition, demand analysis, system analysis, system engineering, value analysis, value engineering and so on.

Tags: Analysis products technology systems advanced value engineering management projects management examination questions systems engineering company duration answers managers bottom-up stages requirements bottom-down Apple Docker Huawei Linux macOS MariaDB Microsoft MySQL NVidia OPPO Reno Shulou Technology Redmi Huawei vpn MySQL