PetroChina's first wind power project started and installed: a total of 18 typhoon turbines with a total installed capacity of 78,000 kilowatts
CTOnews.com, November 23, according to the website of the State-owned assets Supervision and Administration Commission, on November 16, the first wind turbine of PetroChina's first wind power project was successfully hoisted at the construction site of Unit 3 in Qianqing Wind Farm of Jilin Oilfield, marking a new step in the development of Jilin Oilfield from traditional oil industry to new energy integration.
The data show that the project is an important part of the 150,000 kilowatt self-eliminating wind power project under construction in Jilin Oilfield, including 18 typhoon power units with a total installed capacity of 78000 kilowatts, and the estimated annual online power is about 26.0434 million megawatts. Annual equivalent full load 3395 hours.
At present, Jilin Oilfield is accelerating the launch of 150,000 kilowatts of self-eliminating wind power, 550000 kilowatts of wind power and 1.3 million kilowatts of wind power projects.
CTOnews.com learned that PetroChina said the project entered the on-site construction phase in early August this year. Up to now, the foundation, cap and other construction links have been completed, with hoisting conditions, and the construction of other booster stations, high-voltage lines, communication systems and other supporting facilities are in full swing as planned, and power generation is expected to be connected to the grid by the end of the year.